Physical Progress
100%
Approved Budget
KES 9,500,000
Allocated (Current FY)
KES 9,500,000
Disbursed to PMC
KES 9,500,000
Verified Spent
KES 9,500,000
Absorption Rate
100.0%

8-Point Project Transparency Profile

Kenya Constitution Art. 35 Verified

Public transparency index answering the 8 core citizen accountability dimensions mandated by Section 23 of the NG-CDF platform guidelines.

1. What is being built?
Construction of Modern Science Laboratories & Classrooms at Gakawa Secondary School (Education & Academic Infrastructure)
2. Where is it located?
Gakawa Ward • Kieni Constituency NG-CDF
3. Who benefits?
Gakawa Secondary School (~1,650 citizens)
4. How much does it cost?
Budget: KES 9,500,000
5. How much has been disbursed?
Disbursed: KES 9,500,000 • Spent: KES 9,500,000 (Absorption: 100.0%)
6. What is current status?
Substantial / Physical Completion • Verified progress: 100%
7. What bottlenecks exist?
No active execution bottlenecks
8. What documents are available?
Engineering drawings & BOQ summary registered

Project Description & Scope of Works

Standard statutory NG-CDF project implemented in Gakawa Ward, Kieni Constituency, to enhance grassroots public service delivery.

Construction Milestones & Civil Works Schedule

Substructure & Foundation Concrete Works
Weight Contribution: 20%
Verified Complete
Mar 15, 2025
Superstructure Walling & Lintel Ring Beams
Weight Contribution: 25%
Verified Complete
Mar 15, 2025
Roofing Steel Trusses & Prepainted Iron Sheets
Weight Contribution: 25%
Verified Complete
Mar 15, 2025
Finishes, Plastering, Glazing, Electrical & Painting
Weight Contribution: 30%
Verified Complete
Mar 15, 2025

Visual Site Documentation Timeline

Site photographs being compiled by the M&E field team.

Project Statutory Documents & BOQs

No official engineering drawings or BOQ files uploaded for this project yet.

Field Monitoring & Inspection Reports

Routine inspection report scheduled for next quarterly audit.

Execution Challenges & Mitigation Actions

No active contractual or physical execution bottlenecks logged for this project.